Following its partial collapse during heavy rainfall in 2019, Mitcham Bridge on Bishopsford Road was rebuilt and reopened in October 2021

The new bridge is more accommodating to pedestrians and cyclists, and includes:

  • fully segregated cycle lanes on each side of the bridge for northbound and southbound cycling

  • a road that is narrower than the previous carriageway, but wide enough to accommodate A road traffic and abnormal loads (the speed limit is 20mph)

  • a footpath for pedestrians and on the eastern side of the bridge, in addition to the existing wooden footbridge to the west of Mitcham Bridge

  • New segregated cycle lanes on London Road and Bishopsford Road approaches to the bridge

A full timeline is below. Here are some of the most frequently asked questions about the project.

December 2021

Works have largely finished around the site and Transport for London have restored the normal bus service.

Some final works will take place in the New Year, including additional tree planting and restoring the historic parish boundary marker to its previous location.

October 2021

Mitcham Bridge has reopened to pedestrians (upstream footpath), cyclists and traffic.

All other areas will remain under construction and will be finished over the coming weeks.

The bus service will remain on diversion while works are finishing and we will update you when this changes.

September 2021

Work is finishing to resurface and re-clad the bridge in readiness for opening. Development of the cycle lane from the northern side has nearly reached the bridge and will be open the same time as the bridge.

Once the final utilities work has finished, the bridge will be able to be reopened to all traffic shortly after. This website will be updated with an opening date once the utilities work has concluded. Transport for London have confirmed that the 718 replacement bus will continue to serve the area until the bridge has reopened to traffic.

August 2021

Work will be starting on site the week commencing 16 August 2021 to install the cycling improvements along London Road. Thanks to everyone who responded to the consultation. Responses were positive and supportive with some suggested changes; we have amended the design following consultation feedback. This includes:

  • making the junction at Rawnsley Avenue safer for pedestrians and cyclists;
  • having separate spaces for pedestrians and cyclists at the junction of Morden Road and London Road.

We are in the final stages of the bridge construction. The base of the bridge has been constructed across the river and work is continuing to finish the water, broadband and other utilities across the bridge and install the road and pavement surface.

July 2021 - London Road Mitcham cycling improvements

We will be improving cycling facilities along London Road from Bishopsford Road to the junction with Tramway Path. These improvements will involve constructing a segregated cycle lane which will integrate with Bishopsford Road Bridge making it a safer and more attractive route for cyclists. The scheme will also provide fully segregated cycle lanes on Bishopsford Road Bridge itself.

More information can be found in the attached information letter and proposed layout drawing below.

May 2021

During April and May, Land & Water has continued with its works to rebuild Bishopsford Bridge. 

Works have been carried out three metres below ground level in the cofferdam structures, a temporary structure designed to keep water out of the excavation area. This is to create the bridge deck foundations which links the bridge to the ground. Works are now progressing out of the ground in preparation for installation of the main carriageway deck also known as the surface of the bridge.

Land & Water has also worked hard throughout the month to complete rotary bored piling works which are piles that penetrate the ground to support the bridge structure.

The South abutment pour has been completed which means the abutment (the substructure placed at either end of the bridge to help support the bridge arch across the river) is now stabilised. The South abutment pile cap, which provides a stable foundation for the abutment, will now be back filled so that the next stages of the project can be progressed.

The next step in the coming months will be to install the main carriageway deck.

March 2021

During the past month, Land & Water has made significant headway in rebuilding Bishopsford Bridge.

Rotary piling has been completed to the south abutment to remove soil and rock around the structure which connects the deck of the bridge to the ground, with reinforced concrete works about to begin in building the abutment. On the north side, rotary bored piling works are progressing and are over half way complete 

February 2021

Over the past two months, Land & Water has been carrying out essential works to rebuild Bishopsford Bridge.

During February, Land & Water installed temporary steel cofferdams to either side of the River Wandle to prevent ingress from the river into the working area during construction of the new bridge foundations.

Works also started to the south abutment foundations. These drilled, piled foundations are 25m deep and there will be six in both the north and south abutment in order to support the bridge structure.

Following completion of the piled foundations, works will progress out of the ground and the new abutments constructed during the spring.

January 2021 update

We are pleased to announce that Land & Water has been awarded the contract to rebuild the new Bishopsford Bridge.

Land and Water is a specialist wet civil engineering company with expertise in construction and infrastructure around sensitive river landscapes such as at Bishopsford Bridge. SGN completed their site work in December and you will see Land and Water starting on site this month.

The first stages of the construction during January will be to create a bridge structure by installing a temporary cofferdam and piling platforms to allow work to be carried out below the waterline. This will be followed by a pre-cast deck. Machinery has been carefully chosen to reduce noise and ensure that minimal disruption is caused whilst works are taking place.

Land and Water will be contacting local residents living near the bridge to keep them updated with the construction programme.

As this is essential work, Land and Water will be able to continue rebuilding the bridge during the national lockdown by operating in a COVID-19 secure manner, as they did during the demolition of the broken bridge during April – May 2020​.

November 2020 update

SGN works – Rawnsley Avenue and Riverside Drive

SGN are undertaking works to boost the gas supply in the area to avoid gas pressure losses to local residents and businesses.

The SGN works will start on the north side of the bridge, at the end of Rawnsley Avenue and Riverside Drive.

SGN's works are being carried out independently of the bridge rebuild – even if the bridge rebuild was not happening now, SGN would need to restore the gas pressure on both sides of the Wandle to a reliable level for local homes and businesses, particularly for heating and cooking during the winter months.

Please direct any queries towards SGN. The contact details for SGN are:

  • Freephone customer service number: 0800 912 1700
  • Email: customer@sgn.co.uk
  • Post: SGN, Inveralmond House, 200 Dunkeld Road, Perth PH1 3AQ
  • SGN website 

The planning application for the new bridge has now been approved by our Planning Committee (22 October 2020), and we will now approve a contractor to deliver the building work.

You can view the planning application documents online (reference 20/P2438).

Work will now move forwards as detailed in the timeline below.

Outline programme

April - July 2020

  • Broken bridge demolished
  • Public consultation carried out on designs for the new bridge
  • Site surveys undertaken to inform design and construction
  • Procurement starts for the contractor to build the new bridge

August 2020

  • Planning application submitted seeking permission for the new bridge to be built
  • Works continue with gas, water and other utilities to prepare for the construction of the new bridge

September - October 2020

Merton’s planning applications committee considers the application for the new bridge

The council awards the contract to build the new bridge

November 2020 - Spring 2021

Construction of the new bridge

October 2020 update

Thank you to all the people and organisations who gave their views on the new designs for Bishopsford Bridge. This feedback has been incorporated into the designs for the new bridge.

In May and June, 260 people and organisations responded to the opportunity to comment on the designs for the new bridge. Feedback from the consultation has influenced the design to improve safety and give more space for cycling and walking.

Find out more in the October 2020 Newsletter.

If you would like to find out more on the planning application, see the Planning Explorer (reference 20/P2438).

The target date for the planning application to be decided is Merton Council's Planning Applications Committee on 22nd October 2020.

August 2020 update – have your say on designs for the new bridge

The planning application for the new Bishopsford Bridge has been submitted to the council's planning service.

You can view the new designs and details of the planning application on the Planning Explorer.

Have your say by 1 October 2020. The planning application reference number is 20/P2438.

July 2020

The demolition of the broken bridge has been completed. There will be some activity on site and in the surrounding area with the utility companies undertaking preparation works for the new bridge.

Merton’s Design Review Panel have reviewed the designs for the new bridge. Their feedback will be included in the planning application which will be available here from 14th August 2020.

June 2020 update – demolition of Bishopsford Bridge

Demolition is underway on Bishopsford Bridge.

Designs are being prepared for the new bridge. We will submit a planning application in June 2020 and there will be more opportunity to comment on the designs as part of the planning process

May 2020 – consultation on design options

Thank you to all those who contributed to the consultation on the design options for the new Bishopsford Bridge – we've received responses from more than 260 people and organisations.  As well as commenting on the two options, people also told us they want the design to include extra space for cycling and walking. We are reviewing all the comments received in preparation for submitting a planning application for the new bridge in June 2020.

Background report – design options for the new Bishopsford Bridge

March 2020 update

On Tuesday 25 February 2020, Merton Council's Cabinet gave the go-ahead to demolish and re-build Bishopsford Bridge, following its partial collapse into the River Wandle after heavy rainfall last June. 

Following the recent appointment of Land and Water, a specialist river and canal engineering company, work is starting onsite to demolish the old bridge. Construction of the new bridge will begin in the summer with completion set for spring of 2021. 

Start on site and COVID-19

We have carefully considered postponing the full demolition of the partially collapsed bridge in the light of COVID-19.

Continuing with these essential works and demolish the bridge will:

  • significantly reduce the risks of flooding to people's homes and the potential evacuation of nearby properties to communal rest centres. This is something we want to avoid at all costs at any time, but particularly during the COVID-19 outbreak.
  • reduce the risk of further, sudden damage to electricity, gas, water and other utility services that run through the bridge.
  • improve travel times for the emergency services, particularly the fire services from Mitcham Fire Station located near the bridge.

Please be assured that we are working closely with government and Public Health England to ensure we continue to follow the very latest advice and we are as prepared as we can be.

We very much appreciate the support of our partners in the utilities and construction sector in relation to completing this project as soon as possible. Public Health England advice including social distancing will be adhered to on site.

Programme of works

Due to the COVID-19 outbreak, changes to the programme of works have and will continue to take place. Please bear with us, we are doing all we can to keep to the schedule, and we will keep this webpage updated with any changes.

March - April 2020

  • Land and Water to start work on site, removing the broken parts of the bridge.
  • Engage with the local community on the look and details of the new bridge. We were planning to hold community events to talk to residents face to face, but unfortunately, due to the current situation this will now take place online.
  • Seek planning permission for the new bridge.
  • Undertake essential ecology and other survey work.

June 2020 – spring 2021

  • Construction of the new bridge

If COVID-19 guidance changes and we are advised by government to stop work, the council and its partners have an ongoing flood resilience plan in place to ensure flood risk is managed. This includes continually monitoring river levels so that in the event that a flood alert is issued, contingency actions can be put in place quickly.

February 2020 update

News: Council gives the green light to re-build Bishopsford Bridge

Cabinet decision on reopening the bridge

On Monday 24 February 2020 Merton Council's Cabinet considered the preferred approach to reopening Bishopsford Road Bridge and resolved to progress with building a new bridge.

The report has been informed by two studies on the future of the bridge

Newsletter

We are distributing over 3,000 newsletters to local residents and businesses to update on Bishopsford Road Bridge.

January 2020 newsletter

December 2019

We have completed works to stabilise the bridge and are now assessing design and construction options for the repair or replacement of the bridge.

Works on the bridge have been continuing throughout November and December with experts carrying out detailed assessments on-site. As well as stabilising and assessing the structural condition of Bishopsford Road Bridge, the Council has been working to ensure that flood risk is managed throughout the works and looking at options for the permanent plan for the bridge. Independent advisory reports have been commissioned, which will include design options for the repair or replacement of the 200 year old structure, these are expected to be completed early in the New Year after which a timescale will be drawn up for work to be carried out. In the meantime, we are working closely with partners to take every possible step to minimise disruption to residents as they go about their daily lives.

Since the previous newsletter in November we have:

  1. Worked closely with Transport for London to introduce the new number 718 bus route.
  2. Installed CCTV and ANPR cameras, which resulted in six penalty charge notices being issued against vehicles illegally driving over the footbridge.
  3. Overseen essential gasworks carried out by SGN, which are due to be completed before Christmas.
  4. Installed lighting on the footpath in Watermeads.
  5. Met a number of technical specialists onsite to assess the structure of the bridge to inform future construction and consider flood risk.
  6. Installed new hoarding and lighting in preparation for works to start
  7. Worked with utility companies on site to prepare for their services to cross the river Wandle in the future.

November 2019

We started strengthening works on 23 April 2019 as part of the annual highway maintenance scheme. We planned to complete the strengthening works by 22 July. Due to the floods that occurred on 10 June, the river bed and foundations of the bridge were "scoured" (eroded) and therefore undermined. This led to the partial collapse of the northern arch on 14 June.

The southern arch was unaffected and the central arch suffered minor structural damage. Due to the failure of the bridge, the road will continue to be closed until the bridge has been repaired and is safe for pedestrian and vehicular traffic.

Bus services

From Saturday 30 November Transport for London has introduced a new bus route, number 718, between Morden Station and Rose Hill Roundabout running via London Road, Morden Hall Road, Wandle Road and Bishopsford Road. Route 718 will stop at all route 118 bus stops between Morden Station and Wandle Road and all route 280 bus stops between Wandle Road and Rose Hill Roundabout.

Site safety

New hoarding has been put-up around the site, replacing the old fencing.

CCTV / ANPR cameras

CCTV and ANPR cameras are enforcing against vehicles illegally driving over the footbridge. So far we have issued six penalty change notices. Pedestrian guardrails and signs have also been installed as a further deterrent.

Ravensbury Park

Lighting has been installed on the footpath in Ravensbury Park and on the hoardings at the entrance to the footbridge. The path has had a more durable surface laid, vegetation has been cut back and guardrails have been installed. There are no current plans to reduce the height of the brick wall alongside London Road but this will be kept under review.

Ravensbury Park / London Road wall

The brick wall alongside London Road and the park has been raised as an issue where people, particularly children walking to school, feel unsafe. As the evenings get darker, the Council believes that reducing the height of the wall to knee-height will improve security and visibility for pedestrians and cyclists and reduce anti-social behaviour. We are continuing to monitor how we can improve the sense of safety in the area.

Essential gas works

When the bridge partially collapsed, gas mains were re-routed to ensure that properties in Ravensbury Ward continued to receive a gas supply. As the demand for gas has increased, due to the cold weather, Southern Gas Networks are carrying out essential upgrades. Work started on 21 October around The Drive, Arras Avenue, Victory Avenue, Leonard Avenue, Seddon Avenue and Florence Avenue. Temporary traffic lights are in place near junctions. Work is expected to be compete before Christmas.

On-site activities

Thames Water, Southern Gas Networks and other utility companies have visited the site to advice on their preferred permanent route for their services to cross the river Wandle. They have also advised on the measures which will be necessary to keep the utilities running safely now and in the future.

Experts have been assessing the structure of the 200 year old bridge to inform design options for its repair or replacement.

Engineers have reviewed the river and its surroundings to determine what impact the repair or replacement of the bridge would have on ecology, water quality, river flow and flood risk.